This week is scheduled for the electrical & plumbing rough ins and inspections.
Day 1: Framing completed.
Day 2: Additional electrical rough-in.
Day 3: Electrical & framing inspections. Both passed!
Day 4: Plumbing inspection. Passed!
Day 5: Drywall. Great to have insulation and a ceiling again!